Project / Overview
Fabrication and installation of process piping and structural steel for phase 1 of the integrated gas chemical complex in Atyrau Region in 2020–2022. KMS delivered 120,000 inches of carbon and stainless steel piping up to 84 inches in diameter and erected 3,000 tonnes of steel across four key units. More than 4,700 personnel participated over the project, with over 1,100 on site at peak. The scope included turnkey delivery of 50,000 inches of fire-fighting piping for the automated product warehouse.
Explore three ongoing polyethylene project scopes and four completed KMS projects across oil and gas, petrochemicals and energy.