Project / Overview

Installation of process piping and supports, pipe welding, and flange assembly and tightening for the new combined-cycle plant in Kyzylorda in December 2025–January 2026. KMS completed 1,709.5 inches of work in 12 days: 155 pipes, 160 welded joints and 50 bolted connections. The scope included low- and high-pressure lines and silencer installation.

Explore three ongoing polyethylene project scopes and four completed KMS projects across oil and gas, petrochemicals and energy.